Note: Overall totals include all historical data up to and including July 2025.
£15k
£11k
Discount:
£-4k (-26.8%)
£11k
Scope Change:
£0k (0.0%)
£11k
Unrealised:
£0k (0.0%)
£11k
Leakage:
£0k (0.0%)
£11k
Billing:
£-0k (0.0%)
Note: '2025 (Actual)' includes data up to and including July 2025. '2025 (Forecast)' includes data after this date.
| Time Period | Target Fees | Planned Fees | Corrected Fees | Written Hours | Revenue Assigned | Invoiced |
|---|---|---|---|---|---|---|
| 2025 (Forecast) (After July 2025) |
£0k | £0k | £0k | £0k | £0k | £0k |
| 2025 (Actual) (Up to July 2025) |
£0k | £0k | £0k | £0k | £0k | £0k |
| 2024 | £15k | £11k | £11k | £11k | £11k | £11k |
| Pre-2024 | £0k | £0k | £0k | £0k | £0k | £0k |
Note: '2025 (Actual)' includes data up to and including July 2025. '2025 (Planned)' includes data after this date.
| Time Period | Target Fees | Discount | Scope Change | Unrealised Revenue | Leakage | Billing |
|---|---|---|---|---|---|---|
| 2025 (Forecast) (After July 2025) |
£0k |
£0k (0.0%) |
£0k (0.0%) |
- | - | - |
| 2025 (Actual) (Up to July 2025) |
£0k |
£-0k (-26.8%) |
£0k (0.0%) |
£-0k (-100.0%) |
£0k (0.0%) |
£0k (0.0%) |
| 2024 | £15k |
£-4k (-26.8%) |
£0k (0.0%) |
£0k (0.4%) |
£0k (0.0%) |
£-0k (0.0%) |
| Pre-2024 | £0k |
£0k (0.0%) |
£0k (0.0%) |
£0k (0.0%) |
£0k (0.0%) |
£0k (0.0%) |
| Metric | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | £0k | - | - | - | - | - | - | - | - | - | - | - | £0k |
| Planned | £0k | - | - | - | - | - | - | - | - | - | - | - | £0k |
| Corrected | £0k | - | - | - | - | - | - | - | - | - | - | - | £0k |
| Written | - | - | - | - | - | - | - | - | - | - | - | - | £0k |
| Revenue | - | - | - | - | - | - | - | - | - | - | - | - | £0k |
| Invoiced | - | - | - | - | - | - | - | - | - | - | - | - | £0k |
| Metric | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £15k |
| Planned | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £11k |
| Corrected | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £1k | £11k |
| Written | - | - | - | £5k | £3k | £3k | - | - | - | - | - | - | £11k |
| Revenue | - | - | - | - | £8k | £4k | £-1k | - | - | - | - | - | £11k |
| Invoiced | - | - | - | - | - | - | £8k | £3k | - | - | - | - | £11k |
Note: This table lists all allocation tasks for the project. Non-billable tasks and tasks without an assigned resource are excluded from financial summaries but are shown here for completeness.
| Project ID | Task ID | Resource ID | Country | Grade | Billable | Start Date | End Date | Allocations (%) | Target Price | Agreed Price | Corrected Hours | Actual Hours | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| VER1822 | VER1822-1 | 6 | NL | Senior Manager | No | 2024-01-02 | 2025-01-01 | 3% | 262.50 | 192.19 | 56.00 | 56.00 |
Table cells show: Corrected Hours (Planned + Correction) / Actual Hours (Timesheet) / Difference
| Resource ID | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6 |
0.21
0.00
0.21
|
- | - | - | - | - | - | - | - | - | - | - |
0.21
0.00
0.21
|